Project Name: Indirect Preheaters for Ahwaz Desalting plants
Location: Ahwaz, Khouzestan Province
Capacity: Oil heaters capacity are 55000 BPD heating up from 26 to 70 DEG
Scope of Work: The project is consisting of four units of oil and four units of dilution water preheaters with8 MW and 4 MW heat transfer respectively. Oil heaters capacity are 55000 BPD heating up from 26 to 70 DEG. Centigrade and water heater capacity is 5500 BPD heating up from 10 to 80 DEG. Centigrade.
It is also including supply and erection two dilution water pumps in AZ-1.
Type of Contract: EPC
Client: National Iranian South Oil Fields Company NISOC
Contractor(s): Kherad Industry Technical and Engineering Co. (KITEC)
Descriptions: Commencement Date: 2009
Ending Date: Provisional acceptance