Cheshmeh Khosh unit expansion project
 

Cheshmeh Khosh unit expansion project

                 Project Name : Cheshmeh Khosh unit expansion project

 

                       Location : Cheshmeh Khosh, Eelam Province

 

Scope of Work : Project was including below packages:

Eight new streamlines and manifold extension.  Revamping existing Bank A with new instrument and DCS, supply and erection new production bank B & C for salty oil and salty sour oil respectively

Gas gathering piping inside production unit

Three stages gas flares and flare knock out drums

61000 BPD main oil pump

Fire water system including storage tank, electrical and diesel pumps, jockey pump

Complete piping and instruments for production unit

DCS, ESD and F & G systems

9 KM Water pipeline

Drinking water package

 

                  Type of Contract : EPC

 

Client : Iranian Central Oil Fields Company

 

Contractor(s) : Kherad Engineering Company (KEC)

 

                  Commencement Date: Apr. 2006

 

                  Ending Date: Varies with respect to production  schedule Degassing and production tank Feb. 2007

Bank B production: Aug. 2008  , Inlet manifolds Dec. 2009

Bank C production: Mar. 2011  , Main oil pumps: Mar. 2011

Photos
  • Cheshmeh Khosh unit expansion project
  • Cheshmeh Khosh unit expansion project
  • Cheshmeh Khosh unit expansion project
  • Cheshmeh Khosh unit expansion project
  • Cheshmeh Khosh unit expansion project
  • Cheshmeh Khosh unit expansion project
  • Cheshmeh Khosh unit expansion project
  • Cheshmeh Khosh unit expansion project
  • Cheshmeh Khosh unit expansion project
  • Cheshmeh Khosh unit expansion project
  • Cheshmeh Khosh unit expansion project
  • Cheshmeh Khosh unit expansion project
  • Cheshmeh Khosh unit expansion project
  • Cheshmeh Khosh unit expansion project